Contact Town Manager's Office with any questions: manager@actonma.gov (978) 929-6611
Work scheduled for the next few weeks:
WEEK of 1/5
- Cleanup & punchlist - MIG
- Pull wire and install light poles - DAGLE
WEEK of 1/12
- Pull wire and install light poles - DAGLE
WEEK of 1/19
- Pull wire and install light poles - DAGLE
The project is still under construction and will be operating in a temporary traffic pattern until the final paving, which will occur in the spring of 2026.
Thank you for your continued patience and understanding during this multi-year project.
If you have any questions please reach out to the Town Manager's Office at manager@actonma.gov.
Reach out to Economic Development Director, Patricia Costa, if you are a business owner and need assistance in any way! 978-929-6611 or economicdevelopment@actonma.gov – if you’d like to receive updates pertinent to the business community, sign up for Acton’s Business Boost – Acton’s Economic Development newsletter.

Kelley’s Corner Project by the Numbers:
- 2.24 miles of new ADA compliant sidewalks
- 157 new street trees of uniform & appropriate species
- 5 new crosswalks
- 4 pedestrian rapid flashing beacons
- 2 new traffic signals to support safer pedestrian crossings and more efficient vehicle movements
- 4 major intersections redesigned for increased safety
- $18.5+ (million) significant investment of state & federal